NDDC: Uncompleted projects and late budgets

NDDC: Uncompleted projects and late budgets

BY Inalegwu Shaibu

A recent assessment of the activities of the Niger Delta Development Commission, NDDC by the Senator James Manager led Senate Committee on Niger Delta raises multiple questions.

PRior to the establishment of the Niger Delta Development Commission, NDDC in 2000, pressure groups and communal associations in the oil rich Niger Delta region had agitated for an increased share of the oil resources towards addressing the problems of underdevelopment in the area.

Remarkably, most of the agitations by the groups yielded little in terms of attracting development to a region pillaged by the activities of multinational oil companies.

The Federal Government was the biggest casualty of the violence that crept into the region as economic activities were being distorted, resulting in less revenue to government coffers.

And as a way to restore peace in the region and enhance economic prosperity of the nation, former President Olusegun Obasanjo initiated the creation of the NDDC, as a special agency to solely cater for the developmental needs of the Niger Delta region.

The commission took off in 2000 with a clear mandate of developing the oil rich region. The need for quick development of the region was so massive and urgent that since inception, NDDC has awarded well over 5000 projects running into several billions of naira.

Some of the projects include roads and bridges, class room blocks, health facilities and a host of others. But the pace for an accelerated development of the region is being slowed down as most of the projects are yet to be completed. A recent tour of project sites in three Niger Delta states of Rivers, Bayelsa and Delta by the Senate Committee on Niger Delta attested that about 50 percent of projects awarded by the commission are still in the various stages of completion years after being awarded.

Some of the projects visited by the Senator James Manager led committee are Koko-Escravos road and Uzere-Patani road in Delta state, Buguma-Ido-Degema road, and Igbiri-Abam link road in Rivers State amongst others.

The Igbiri-Abam link road awarded in 2009 at the cost of N5.13 billion to Madmoselle Nigeria limited has about 22 percent completion, while the 16 kilometer Uzere-Patani road has reached 58 percent completion.

Dr. Oboh blamed the slow pace of work on the projects on lack of proper monitoring by the commission and inadequate funding. He said the NDDC has less than 20 engineers thereby making it difficult to effectively monitor the projects.
According to him, “We have in NDDC as we speak less than 20 engineers and we will agree that that number cannot chase all the projects.”

“Basically the root cause of the matter is that we are actually not visiting project sites, we were receiving reports that were actually not on ground. Now like we said there is a turning point now in NDDC. We are going to visit project sites so that with our eyes we can see what the contractors are actually doing and I believe that if we do this regularly there will be change, projects will be delivered and the region will be good.”

Rivers State governor, Rotimi Amaechi, who hosted the Senators, also expressed dissatisfaction with the slow pace of development by the NDDC.

Governor Amaechi observed that the entire Niger Delta region is replete with uncompleted projects, which does not justify the huge of amount of resources pumped into the region.

“The different states in the Niger Delta region are littered with poor quality jobs and uncompleted projects. In an attempt to service the officials, we are getting poor quality jobs. We told the NDDC, go and build railways that connect the entire Niger Delta region, from Cross River to Akwa Ibom, to Rivers to Bayelsa, to Delta.”

Abandoned projects
Dr. Oboh agreed with the governor noting that the commission has too many abandoned projects which cannot bring the much deserved development to the region.

He said the commission aware of the problems, has realigned its objective by stopping the awards of new projects to making sure that existing projects are fully funded and completed.

“With our new style of budgeting, we are providing for funds, and we believe that the contractors will also begin to change their styles and God willing I am sure that we will be delivering more projects than we have seen in the past.”
Senator Manager on his part tasked the commission to fast track its budgetary process to ensure quick passage by the National Assembly.

He noted that the NDDC budget comes too late to National Assembly thereby leading to late passages, which in turn frustrate execution of projects.

He said, “The NDDC was set up for a special purpose. The NDDC has a fundamental problem. The problem came to the epic last year when the NDDC had to present the 2011 budget towards the end of 2011. It was a very hard one. Not many Nigerians understood why that had to be.

“This is 2012; the entire National Assembly warned that the budget for 2012 must come early enough. The 2012 budget is yet to arrive the National Assembly and that is not good enough for the region, the earlier the better.”