Load rotation: IBEDC apologises to customers for inconveniences

Kindly Share This Story:

IBEDC appeals for calm in Lalupon community over low power supply

By Adeola Badru

Ibadan Electricity Distribution Company (IBEDC) has apologised to its customers in Magboro, Ibafo, Mowe and environs for the inconveniences on the load shedding arrangement ongoing in the areas.

This is as the distribution company assured that the arrangement is a temporary measure, adding that it is already working assiduously with the Transmission Company of Nigeria (TCN) to proffer a lasting solution to the power supply problem in the area.

The company offered an apology while reacting to a public letter by the IBEDC Consumers Forum, Ibafo on the rejection of the new load-shedding formula implemented from the 15th of March, 2021.

A statement issued by the Chief Technical Officer, Engr. Akin Abiodun on behalf of the management, also explained that a rising increase in population in the axis has created an attendant rise in energy consumption making the initial allocation to the axis grossly inadequate.

Also read: Insurgents vandalise towers, cut power supply to Maiduguri, environs-TCN

Abiodun said: “The supply to Ibafo originates from a 33kV feeder which radiates supply from Oke-Aro Transmission Station through Magboro, Makogi, Oke-Afa to Ibafo, Asese, Orimerunmu, Pakuro, Lotto and Mowe axis and environs.”

“The current load demand for the axis for an equitable power supply is 35 Megawatts, but the allocated energy from Oke-Aro TCN is 13 Megawatts, which was the initial arrangement based on how sparsely populated the communities where a few years ago.”

“The increase in population has created an attendant rise in energy consumption making the 13 Megawatts grossly inadequate.”

“As part of efforts to ensure an even distribution of power supply to the communities, IBEDC Management had met and written to the Transmission Company of Nigeria (TCN) requesting for an increase in load allocation to the axis, the TCN management however explained that all the transformers at the station are already overloaded, but that plans are in place for the upgrade of the Substation.”

“IBEDC then went further to request for diversion of excess load on another feeder to Ibafo 33kV feeder, the request is yet to be granted.”

“Furthermore, IBEDC has commenced radiating another feeder from the recently commissioned Kobape Transmission Station in Abeokuta to Mowe/Ibafo to relieve the load demand of the area and that is expected to take effect later on in the year.”

“The feeder is overloaded, and it trips frequently. Frequent tripping of feeders shortens the life of Circuit Breakers, and this necessitated the need for load shedding methodology that will promote an amicable and mutual benefit to our substation equipment and all the communities concerned.”

“The decision to review the three shifts load shedding management to four, for the fair and quality power supply was duly discussed with the community leaders, and agreed upon by the leaders before its commencement on the 15th of March 2021.”

“IBEDC as a customer-centric company that has the interest of her customers at heart apologizes for all the inconveniences this new load shedding arrangement might have caused our esteemed customers in Magboro, Ibafo, Mowe and environs.”

“The arrangement is only temporary as IBEDC and the Transmission Company of Nigeria, TCN is working assiduously to proffer a lasting solution to power supply problem in the area.”

Vanguard News Nigeria 

Kindly Share This Story:
All rights reserved. This material and any other digital content on this platform may not be reproduced, published, broadcast, written or distributed in full or in part, without written permission from VANGUARD NEWS.

Disclaimer

Comments expressed here do not reflect the opinions of vanguard newspapers or any employee thereof.
Do NOT follow this link or you will be banned from the site!