Eratic Power: Anambra, Imo get new injection substations

By Peace Onyeukwu, Araino Oke & Thomas Ejiemere

In a bid to improve power supply in South Eastern part of Nigeria, Enugu Electricity Distribution PLC (EEDC, has installed and upgraded new injection substations in Imo and Anambra State.

Specifically, the projects include the construction of a 1X7.5MVA Injection Substation at ABS, Awka, and upgrading of the 7.5MVA Injection Substation at Agu Awka to a 15MVA; while in Imo State, approval has been obtained for the construction of a new Oguta 33KV line valued at over N140 million which will radiate from Egbu Transmission Company of Nigeria (TCN).

The company Head of Corporate Communication, Enema Ezeh, said that, the projects were necessitated by the challenges of poor electricity supply within the areas due to over loaded feeders.

“The 1X7.5MVA Injection Substation at ABS, Awka, will be ready for commissioning within the first quarter of 2018, is expected to improve electricity supply to Okpuno, Isuaniocha, Mgbakwu, Urum and Amanuke communities and the university community.

READ ALSO: 24 hours electricity offends residents

“The upgrade of Agu Awka Injection Substation is expected to address the electricity supply challenges and boost supply to Awka Industrial Layout, Ifite, Agu-Awka GRA, parts of Nkwere Awka, UNIZIK, Amansea, Ebenebe, Ugbenu and Ugbene communities.

“Also in Owerri, work will soon commence on the new Oguta 33KV line which will take care of customers in New Owerri, World Bank, Concord Hotel area, Iret e Community and industrialists within the area. Effort has equally been made to radiate a dedicated feeder to improve availability to Alex Aluminium and other industrialists within the cluster.

“It will be recalled that last year, EEDC delivered major network enhancement projects ranging from deloading of feeders, deployment of relief transformers and replacement of failed transformers. In Enugu State, EEDC completed and commissioned the 1 x 7.5 MVA Nike Lake Injection Substation at Nike, which greatly improved electricity supply to the entire Nike area and parts of Abakpa.”

In a related development, EEDC constructed three feeders to improve supply to her customers in Nsukka, they are the UNN 33KV, Nru 33KV and Wilson 11KV feeders. This has significantly improved power supply to the area and resulted to the deloading of Eha Amufu 33KV line.

According to Ezeh, the company x-rayed its network; identifying areas that need critical attention with a view to strategically address them. It is not possible to attend to all the challenges at the same time, but there is a conscious effort by the business to deal with them and that has informed the investments in the network.

These investments underscore our organisation’s commitment to strategically addressing the power supply needs of our customers, we are therefore hoping that they will reciprocate this gesture by ensuring they pay their electricity bills as and when due.

It is also hoped that they join hands with the EEDC in safeguarding the power installations serving them from being vandalized, and desist from acts such as meter bypass and energy theft.