How protests stalled $1.2bn 700mw Zungeru power project — Director
THE Senate was, yesterday, told that delay in payment of compensation and resettlement of host community, which led to blockage of access roads to the main dam site, quarries and borrow pit areas by the villagers around the $1.2 billion Zungeru Hydroelectric Power Project, has stalled the completion date by two years.