Electricity: GenCos fail to generate 3,568 megawatts due to gas shortage

Kindly Share This Story:

Electricity: GenCos fail to generate 3,568 megawatts due to gas shortage

Electricity Generation Companies (GenCos) comprising gas-fired and hydro stations said they could not generate 3,568 megawatts of electricity on Wednesday due to the unavailability of gas.

This information was made known in a daily energy report by the Advisory Power Team, office of the Vice President, a copy of which was obtained by News Agency of Nigeria (NAN) in Abuja on Thursday.

The report also noted that 110 megawatts of electricity was not generated due to unavailability of transmission infrastructure during the period.

Similarly, it said that 603.3 megawatts of was not generated due to high frequency resulting from unavailability of distribution infrastructure.

ALSO READ: Six million electricity consumers on estimated billing — NERC

The report, however, said that the GenCos released an average of 4,149 MegaWatts/Hour of electricity into the national grid on Wednesday.

It said  the electricity sent out by the GenCos was down  by 226.51 megawatts from the 4,376 released on Tuesday.

The report revealed that the power sector lost an estimated N2,055 billion on Wednesday due to insufficient gas supply, distribution, and transmission infrastructure.

On sector reform and activities, it said that the dominant constraint for Wednesday was unavailability of gas.

The report said the peak generation attained on Wednesday  was 4, 640 megawatts.

[NAN]

Vanguard News Nigeria.

Kindly Share This Story:
All rights reserved. This material and any other digital content on this platform may not be reproduced, published, broadcast, written or distributed in full or in part, without written permission from VANGUARD NEWS.

Disclaimer

Comments expressed here do not reflect the opinions of vanguard newspapers or any employee thereof.
Do NOT follow this link or you will be banned from the site!